How to switch 3PLs without missing a day of shipping

Run both warehouses at once for one to two weeks, sign the new one before you give notice, and cut order routing over on a set timestamp. Here are the notice periods, the three ways to move stock, the five-step cutover, and what it costs to leave.

BoxHero Team

November 19, 2026

5 min read

How to switch 3PLs without missing a day of shipping

You switch 3PLs without missing a day of shipping by running both warehouses at once for one to two weeks. Sign the new warehouse first. Send it a slice of stock, ship a test order, then move your order routing over on a set date and time while the old warehouse ships down what it still holds. Your current contract's notice period, usually 30 to 90 days, sets the whole calendar.

Why the notice period sets the calendar

Four stat cards with the numbers that set a 3PL switch calendar. Most 3PL contracts require 30 to 90 days of written notice before you can leave. The overlap period is one to two weeks, with best sellers kept at the old warehouse during the move. Most contracts give 30 to 60 days after termination to remove inventory. Handling charges on the way out run $2 to $5 per case.
The four numbers that set a 3PL switch calendar. Notice period from Prep Prime, August 2026; overlap from Fulfillrite, July 2026; removal window and handling charges from Red Stag, updated August 2026.

Most 3PL contracts call for 30 to 90 days of written notice before you can leave, according to Prep Prime's August 2026 guide. Red Stag's switching guide (updated August 2026) says to secure the new 3PL and confirm its onboarding dates before you give notice to the current one. If you give notice first, the clock runs while you are still shopping.

Inside a 90-day window, Racklify budgets about four weeks for sourcing and contracts, about three weeks for integration and testing, and about two weeks for the physical move and ramp. That is close to 63 days of real work, leaving about four weeks of slack. On a 30-day notice there is no slack. Fulfillrite (July 2026) puts the whole switch at about a month end to end and calls 30 days the common notice period, so a 30-day exit is possible, but only if the new warehouse is already set up when you send the letter.

Three ways to move the stock

The overlap is where the no-missed-day promise lives. ShipMonk lays out three ways to move inventory, and each trades downtime against cost.

MethodHow it worksDowntimeBest for
Hard switchPull everything from the old warehouse and ship it to the new one in one freight moveDays, while stock is in transit and being receivedLow order volume, few SKUs
Split transferSend part of each SKU, such as half, to the new warehouse; keep shipping from the old one until the new one is live, then move the restNone if the two counts are managedMost brands with steady daily orders
New stock directPoint the next supplier shipment at the new warehouse; let the old one sell down to zeroNoneBrands with a replenishment landing soon, few SKUs

The split transfer is the one that fits most brands. Fulfillrite's version keeps a one to two week buffer of best sellers at the old provider so orders keep moving while the main freight shipment is received. Before anything moves, Fulfill.com's checklist (updated September 2026) says to count at both ends and compare against the old 3PL's last inventory report, and to pull dead SKUs, damaged units and old packaging before the move so you do not pay freight on things you will never ship.

The cutover, step by step

  1. Export SKU-level counts from the old warehouse the day you give notice. Photograph condition on receipt at the new one. Red Stag says to reconcile any count difference within 24 hours.
  2. Map every SKU, bundle and kit in the new warehouse's system, then ship one real test order through the storefront integration and confirm the tracking number writes back.
  3. Pilot. Red Stag routes 5 to 10 percent of orders to the new warehouse for one to two weeks, then ramps 10, 25, 50, 75 and 100 percent, pausing if accuracy drops under 99 percent or the error rate passes 2 percent.
  4. Set a hard cutover timestamp. Orders placed before it ship from the old warehouse; orders after it ship from the new one. That is Fulfillrite's rule, and it keeps any order from being claimed twice or by nobody.
  5. Wind down. Ship the remaining buffer stock, settle the final invoice, export your order history, and run a closing count.
Five numbered steps for the cutover from one 3PL to another. Step one, export SKU-level counts the day you give notice and reconcile any difference within 24 hours. Step two, map every SKU, bundle and kit, then ship one real test order through the storefront integration. Step three, pilot 5 to 10 percent of orders for one to two weeks, then ramp 10, 25, 50, 75 and 100 percent. Step four, set a hard cutover timestamp so orders before it ship from the old warehouse and orders after it ship from the new one. Step five, wind down by shipping the buffer stock, settling the final invoice, exporting order history and running a closing count.
The five-step cutover. Reconciliation, pilot and ramp figures from Red Stag, updated August 2026; the hard cutover timestamp from Fulfillrite, July 2026.

What it costs to leave

Three charges show up on the way out, and none of them is on the rate card you signed. First, the offboarding fee. Fulfyld describes it as covering the labor to locate, pick, stage and repackage every SKU for transfer, plus closing out billing and any data export. Red Stag puts handling at $2 to $5 per case, so a 1,000-case move runs $2,000 to $5,000. Second, early termination. Red Stag reports lump-sum termination fees of two to three months of average billing when you leave a fixed term early, and final invoices due within 7 to 15 days of the notice. Third, the lien. Under UCC section 7-209, a warehouse can hold your inventory against unpaid charges, so pay the last invoice before the last truck is booked. Red Stag says most contracts give you 30 to 60 days after termination to remove inventory.

Add the cost of two warehouses at once. Red Stag budgets 30 to 90 days of paying two 3PLs and onboarding fees of $1,000 to $10,000 at the new one. Any monthly minimum at the old warehouse keeps billing during the overlap, which is one more reason minimums deserve a hard look before you sign anywhere.

When not to switch

Do not switch into peak. Red Stag names February to March and August to September as the best windows and says to stay 60 to 90 days away from peak season. Fulfill.com calls January to March the ideal transition period. If you are reading this in November, run the audit now, sign in January, and move in February. Our BFCM checklist covers how to hold the current warehouse together until then.

How a switch runs at Remsen Avenue

We built onboarding around the overlap. Setup takes under an hour, and most brands go live the same week. Receiving is $0, there is no integration fee and there is no contract, so running us alongside your old warehouse for two weeks costs you the storage and the orders we ship, nothing else. Inbound pallets or parcels are counted and shelved the day they land at 905 Remsen Ave in Brooklyn, with any discrepancy reported before receiving closes. Units without barcodes get one at intake. We ship a test order before you switch over, and plenty of brands start with one channel or a slice of SKUs and widen from there. Once live, orders in by 3:30pm ET ship the same day at 99.9 percent pick accuracy. If you ever leave, tell us and we will help you move your inventory out. For the larger question of whether to outsource at all, start with the five numbers that decide it.

Source:

Want this handled for you?

Tell us your orders a month and units per order. You see a per-order price before you commit to anything.

Your brand's warehouse partner. We do everything outside of selling the products you own.

905 Remsen Ave, Brooklyn, NY

929-900-1101

© 2026 BoxHero Logistics Corp.

Fulfillment from NYC. Cutoff 3:30pm.